Pro Football Hall of Fame New Stadium Complex

Canton, Ohio

Project Description

Over the course of years 2016-2017, Beaver Constructors, Inc. proudly partnered with the owner, developer, and construction manager of this project to perform multiple work scopes of both Phase 1 and Phase 2 of this 23,000-person capacity stadium renovation. Demolition, sitework, underground utilities, drilled shafts, foundations, soil nail retention wall, site concrete, interior concrete, rough carpentry, and finish carpentry work, totaling $10 million dollars, was all self-performed by Beaver. Beaver Constructors worked multiple shifts and supplied hundreds of men and women to help complete this project on schedule for the Hall of Fames’ enshrinement festivities.

Project Highlights

  • 40 drilled shaft caissons
  • 19 micropiles
  • 8 ea. 84” diameter light pole caissons
  • 1,000 cy grade beam concrete
  • Demolition of existing stadium stands and press box structure
  • Construction of concrete retaining wall
  • Lower existing stadium field 14’