Visit Our Other Beaver Family Companies
Beaver ExcavatingStone Products

Shearer’s Foods – Millennium Plant Addition

Massillon, Ohio

Project Description

Beaver Constructors Inc., was awarded the Design-Build contract for Shearer’s $5.5 million warehouse addition and exterior work project. Completed in 2021, the 50,000 square foot addition was a pre-engineered metal building with 8 docks and other necessary elements to allow it to operate seamlessly with their existing infrastructure. Beaver also relocated the existing oil and corn unloading ramps, along with their compactor. Beaver also poured 65,000 SF of concrete for their exterior paving and truck staging area.

Project Highlights

  • Design-build delivery method
  • 50,000 sf, 32′-high, Varco Pruden pre-engineered building
  • 65,000 sf exterior concrete paving/truck staging area
  • Interior shipping offices, breakroom, restroom
  • 8 fully-integrated continuous dock pits featuring stand-up dock levelers and overhead door with touchscreen controls
  • Fully sprinkled
  • Heating and cross-ventilation
  • LED lighting
  • Site development included relocation of the facilities existing electrical switchgear, fire line loop, storm sewer, and waterline with two scheduled shutdowns
  • Relocation of the oil unloading ramp, corn unloading, and compactor